Project description
Back-up Metering Scheme (I) Installation of Quality Loop at Sapele, Amukpe & Oben Flow Station. (II) Installation of GE Ultrasonic Flow Meter, Solar Power system, Manhole & Harass Fence at Rapele & Amukpe Manifold.
Client: Seplat /SPDC
Duration: July 2010 – November 2010 (4 Months)
Scope of Work, Briefly:
- Installation of GE Ultrasonic Flow meter (Clamp on Around 24’’ Pipeline.
- Installation of Solar power system as source of power for the Clamp on GE Ultrasonic flow meter.
- Construction of Manhole & Harass Fence around the UFM.
- Installation Of Quality Loop System comprising of BS & W Monitor, Control Panel.
- Pull and install Electrical Cable and Instrument cable for the quality loop system .
- Fabrication and installation and hook up of piping spools for complete erection of quality loop system.
- Pre-commissioning, start up
- As-Built Documentation & Close out report.